Plan Update Timeline

Public Input Phase


  • December 2016 – Public Online Survey
  • January 2017 – Public Input through Community Conversation meetings (Round 1)
  • February 2017 – Community Conversation meeting (Round 2) – prioritize issues
  • See Plan Update Page for further details

Draft Document Plan Phase 


  • February 2017 – March 2018

Plan Review & Approval


  • March 2018 – 60 day draft plan agency & public review period
  • May 2018 – Review and respond to comments
  • June 2018 – Hold public hearing
  • June/July 2018 – 90 day state agency final review
  • December 2018 – BWSR plan approval
  • January 2019 – County Board adopts plan

Click on timeline to enlarge

RevisedTimeline